Matt “Almost Resident” Johnson is definitely into PSA these days, learning and sharing what he learned.
Here’s a quick reference for anyone interested in when the Actuals are created during a Project in PSA. Maybe this will save someone a bit of investigation time or make things clearer in their mind.
Time and Materials Project
Steps | Actuals Created |
---|---|
Resource adds time/expense | |
Resource submits time/expense | |
Time/expense approved by PM | Actual created – Cost Actual created – Unbilled Sales |
Invoice created for all unbilled sales | |
Invoice confirmed (sent to customer) | Actual created – Unbilled Sales (reversal of the previously created unbilled sale) Actual created – Billed Sales |
Invoice marked as Paid |
Notes:
- Actuals can be seen against either the Project, the Contract or the Invoice
- Actuals will not be created if the contract is not associated with the project even if time is submitted and approved.
Fixed Price Project
Steps | Actuals Created |
---|---|
Resource adds time/expense | |
Resource submits time/expense | |
Time/expense approved by PM | Actual created – Cost |
Milestone marked as ready for invoicing | |
Invoice created for Milestone Amount(s) | |
Invoice confirmed (sent to customer) | Actual created – Billed Sales (Transaction class == Milestone) |
Invoice marked as Paid |
Notes:
- Actuals can be seen against either the Project or the Contract. Only the Billed Sales (Milestone) Actual will be associated with the Invoice.
- Out of the box Milestones must be marked as Ready for Invoicing manually.
- Although a milestone can be associated with a single Task, once this task is completed 100% it doesn’t automagically mark the Milestone as Ready for Invoicing.
- A Task can actually be associated with multiple Milestones but a Milestone can only have one Task associated with it.